Planning Tool

Generate a scrollable Gantt-style planning view from JSON files describing tasks, milestones, and deliverables.

Quick start

Static HTML export

python generate_plan.py data/aircraft-design -o output/aircraft-design.html -t "Aircraft Design"

Open output/aircraft-design.html in a browser.

Interactive web editor

Install dependencies (first time only):

pip install -r requirements.txt

Start the local editor:

python -m app

Open http://localhost:8000. Options: --port 8000, --plan aircraft-design, --host 127.0.0.1.

Dual workflow (web + Cursor)

Both the web app and generate_plan.py read the same JSON files under data/<plan>/ (one file per item). The disk is the source of truth — there is no database.

  1. Edit in the browser — drag task bars to move or resize (snaps to whole days, pushes dependent items forward), click any item to edit JSON in the side panel, right-click empty chart area to create a new task (3-month default duration).
  2. Edit in Cursor — change any data/aircraft-design/*.json file directly; the web app polls every 3 seconds and reloads (or prompts if you have unsaved panel edits).
  3. Static export — python generate_plan.py still produces a read-only HTML file using templates/gantt.html.

New tasks are saved immediately as task-NN-slug.json. Dragging a task earlier than its predecessors allows is clamped to the day after the latest predecessor ends.

JSON format

Each file is one object. Required fields depend on type:

Field Task Milestone Deliverable
id ✓ ✓ ✓
type "task" "milestone" "deliverable"
name ✓ ✓ ✓
start, end ✓ (YYYY-MM-DD) — —
date — ✓ ✓
predecessors optional array of ids optional optional

Additional fields (description, assignee, status, priority, tags, notes, color, etc.) are shown in the hover tooltip. Any extra keys you add are also displayed.

Milestones render on the timeline header (diamond + label) with a vertical line spanning the full chart height. Tasks and deliverables occupy rows below.

To share a row, use the same "row" or "group" on tasks/deliverables.

If items on the same row overlap in time, the row expands into subrows (stacked lanes with light divider lines).

Example task

{
  "id": "design",
  "type": "task",
  "name": "System design",
  "description": "Architecture and wireframes.",
  "start": "2026-06-16",
  "end": "2026-07-04",
  "predecessors": ["req-spec"],
  "status": "planned",
  "assignee": "Bob"
}

Example: parallel tasks on one row

{
  "id": "frontend",
  "type": "task",
  "name": "Frontend build",
  "start": "2026-07-07",
  "end": "2026-08-01",
  "group": "implementation",
  "row_label": "Implementation"
}
{
  "id": "backend",
  "type": "task",
  "name": "Backend build",
  "start": "2026-07-07",
  "end": "2026-08-15",
  "group": "implementation"
}

Both tasks appear on one row because they share "group": "implementation".

Example milestone

{
  "id": "design-review",
  "type": "milestone",
  "name": "Design review",
  "date": "2026-07-04",
  "predecessors": ["design"]
}

Example deliverable

{
  "id": "mvp-release",
  "type": "deliverable",
  "name": "MVP release",
  "date": "2026-08-22",
  "predecessors": ["implementation"],
  "color": "#059669"
}

Prompt for Cursor / LLM

Copy this when asking an LLM to create planning JSON files:

Create one JSON file per planning item for a Gantt chart tool. Follow the schema in schema/planning-item.schema.json. Use type: task (with start and end), milestone (with date), or deliverable (with date). Each item needs a unique id. Link items with predecessors (array of ids). Include rich metadata: description, assignee, status, priority, tags, notes. Dates as YYYY-MM-DD. Save files in data/<project-name>/ with type-prefixed filenames like task-01-flight-loads.json, milestone-00-kickoff.json, or deliverable-07-primary-structure-external-loft.json.

Chart behaviour

  • Tasks — horizontal bars, width proportional to duration.
  • Milestones — orange diamonds at a point in time.
  • Deliverables — green circles at a point in time.
  • Dependencies — straight diagonal arrows from predecessor end to successor start.
  • Tooltips — hover any item to see all JSON fields.
  • Scrolling — vertical scroll for rows; horizontal scroll for the timeline.
  • Zoom — use Ctrl + scroll (or ⌘ + scroll on Mac) over the chart to zoom toward the cursor; +/−, slider, and Fit in the header.

CLI options

python generate_plan.py [data_dir] [-o OUTPUT] [-t TITLE] [--template PATH]
Argument Default Description
data_dir data/example Folder of *.json item files
-o, --output output/plan.html Generated HTML path
-t, --title Project Plan Browser title and header
--template templates/gantt.html HTML template

Project layout

Aircraft_Planning/
  generate_plan.py         # JSON → static HTML (uses plan_logic)
  plan_logic.py            # Shared load, validate, assign_rows, cascade
  app/                     # Interactive web editor (python -m app)
  templates/
    gantt.html             # Read-only chart template
    gantt-editor.html      # Interactive editor page
  schema/                  # JSON schema for validation
  data/aircraft-design/    # Planning items (one JSON file each)
  output/                  # Generated static HTML
  requirements.txt         # fastapi, uvicorn, jsonschema

Static export uses Python 3.9+ stdlib only. The web editor requires pip install -r requirements.txt.